Active Neighbourhood Dates

Active Neighbourhood online feedback deadline 28 October 2020

Road Blocks / “Modal Filters” trial will run from 19 December 2020 to 19 June 2021

UPDATE: The Manchester City Council website did not mention any dates initially, then within the last week the dates were added. It seemed the dates had been removed but actually an extra page of text was added to the MCC website on 7th October HERE that still includes the dates.

A contact email for the project has also now been added: levyburnageproject@manchester.gov.uk


Manchester City Council still hasn’t actually informed anybody about the new plans and consultation on the proposed Active Neighbourhood but it has set a deadline for feedback.

Letters were promised to all residents, businesses, schools and community groups but so far nothing has been sent out. We were also promised a phone line to make comments and that has not yet been provided and an email address which so far doesn’t seem to exist. The new website for commenting is only available in English. No posters or information have been put up in the area informing people about the online consultation. So the only way to comment on a scheme the council hasn’t officially told anyone about yet is online HERE.

Regardless of not telling anyone about the new plans apart from a tweet from our MP, Afzal Khan, that was shared by some councillors the council has now provided a deadline when the online consultation will end on 28th October. So we won’t be able to comment on a plan the council hasn’t told anybody about after 28th October.

There are now 25 individual road blocks / “modal filters” on the new plans in Phase 1 covering Levenshulme. The Commonplace website says temporary crossings and traffic calming will be included the trial but there is no evidence of these on the new plans although part of the online consultation invites comments about these. A summary of the new plans is available HERE.

Note that the project has now been renamed “Levenshulme and Burnage Active Neighbourhood”. When it was called Levenshulme Bee Network it included part of Burnage. Now it is called Levenshulme and Burnage Active Neighbourhood that part of Burnage is now excluded from the trial starting in December.

The part of Burnage included in the project is now identified as “Phase 2”. The project claims it will reduce traffic in the area but the council says the Burnage area has now been excluded from the December trial “…because of the density of schools in the Cringle Brook (Phase 2) area, and issues with traffic congestion…” which is a little confusing.

The Phase 2 area covers part of Burnage Ward and was identified previously as “Cringle Park Area”, not “Cringle Brook” as the council website says. The road blocks / “modal filters” that were in the previous plans in what is now Phase 2 have been removed from the new plans and you are invited to propose ideas for Burnage Ward. No timeline is available for Phase 2.

The project was paused in the summer to allow for further and more extensive engagement with the community. The July statement from Levenshulme councillors is below for reference. Since then a new Project Manager was appointed by the council, new plans developed that seem to be almost identical to the original plans despite them receiving considerable opposition from our community and the Burnage section of the project has been removed from the trial despite Sustrans (who developed the plans for the council) saying the whole scheme needed to be trialled or it wouldn’t work.

The whole thing is ever more confusing but further updates will be provided as things develop to try and keep people informed.

Leave a Reply